Home · Our House · Construction Progress · March through June



Construction Progess

March Through June, 2007



March, 2007













March 1, 2007
The date we were to have begun.  Weather has prevented the contractors from starting the prep work.
The Property before construction
March 13, 2007
No real construction has begun.  These are pictures of the property before we started.
Driveway Entrance Mysterious Stake
March 28, 2007
A Mysterious Stake has appeared in the middle of the driveway.



April, 2007


Initial Grading Underway
April 14,2007
At Last! We've got a 'Dozer sighting!  The initial grading for the driveway is underway.
Driveway Final Grade
April 18, 2007
Rough Grade for Driveway is done!
Driveway Rock and Basement Excavation
April 19,2007
Driveway is rocked and Basement is excavated
Excavation Complete
April 21, 2007
Driveway is done for now and the excavation is complete

Concrete Footing Forms Complete
April 23-28, 2007
Forms for the footings.
Concrete Pour
April 30, 2007
Pouring the concrete for footings.




May, 2007

Footings Finished
May 1, 2007
Footings finished
basement Wall Forms
May 3, 2007
Forms going up for the basement walls.
Basement Walls Complete
May 4, 2007
Basement Walls Completed

05/09/07 Plumbing Progress
May 9, 2007
Basement Walls Completed
Plumbing Waterproofing and Drainage
May 10, 2007
Waterproofing, Drainage and Rough-Ins
Basement Floor poured
May 11, 2007
Basement Floor Poured

Basement Floos Finished, Additional Grading
May 12, 2007
Basement Floor Finished, Additional Grading

Septic Lines Run
May 17, 2007
Septic Lines Run

Garage Floor Being Poured
May 21 - May 23, 2007
Garage Floor Poured

Transformer and Temporary Pole
May 25, 2007
Electrical Service Buried to House

May 29 - 30, Electic Service COnnected
May 29, 2007
Electrical Service Connected, Windows Arrive






June, 2007


Basement Walls Framing
June 4, 2007
Framing Begins

Basement Framing Finished
June 5, 2007
Basement Framing Finished, Sub-Floor Installed

06/07/07
June 6 - 7, 2007
Framing Main Floor

Main Floor Framing 06/08/07
June 8, 2007
Main Floor Framing, almost complete

First Floor and Garage Framing Finished
June 11, 2007
Main Floor and Garage Framing complete

6/12/07 Second Floor Framing
June 12, 2007
Framing Second Floor, Geothermal Ground Loop Installed

06/13/07 Second Floor Framed
June 13, 2007
Second Floor Framing Complete

06/14/07 Roof Truses Placed
June 14, 2007
Roof Truses Placed

6/15/07 Roofing Contiunes, Front Porch Poured, Retaining Walls Finished
June 15, 2007
Roofing Contiunes, Retaining Walls Finished

06/18/07 Roofing Continues
June 18, 2007
Roofing Continues

06/19/07 Roofing Continues
June 19, 2007
Roofing Continues

06/20/07 Roofing Continues
June 20, 2007
Roofing Continues

06/21/07 Roofing Continues, Shingles Arrive
June 21, 2007
Roofing Continues, Shingles Arrive

06/22/07 Window Install Beginning
June 22, 2007
Roofing on Hold, Windows Installed

06/25/07 More Windows Installed
June 25, 2007
More Windows Installed

06/26/07 Singles, Plumbing, Etc
June 26, 2007
Shingles being installed, Plumbing Started

06/27/07 Roofing Finished, Windows Continue
June 27, 2007
Roofing Finished, Windows Almost Finished

06/28/07 Fireplace Installed
June 28, 2007
Plumbing Contiunes, Fireplace Installed

06/29/07 Deck Started
June 29, 2007
Electrical Wiring Started Deck Started

06/30/07 Electrical Continues
June 30, 2007
Electrical Work Continues








Return to our Home Page or Go Back to Our New Home or Go to Most Recent Construction Progress



 Mac and the Mac logo are trademarks of Apple Computer, Inc., registered in the U.S. and other countries. The Made on a Mac Badge is a trademark of Apple Computer, Inc., used with permission.

Made on a Mac

This web site and all content is © 2007 John D Innis

Email me Here!