John and Heather Innis

Home · Our House · Construction Progress



Construction Progess

Most Recent Updates, July and August, 2007



Marc through June, 2007

March - June, 2007


July, 2007


07/04/07 Duct Work Started
July 4, 2007
Ductwork In Progress

07/09/07 Furnace Install Continues
July 9, 2007
Furnace Install Contunies, Central Vac Rough In

7/11/07 Ductwork Continues
July 11, 2007
Ductwork Continues

07/12/07 Ductwork Complete
July 12, 2007
Ductwork and Furnace Install Complete

07/14/07 Views From Up High
July 14, 2007
Views From Up High

07/16/07 Brickwork Started
July 16, 2007
Brickwork Started, Insulation in Progress

07/18/07 Drywall Arived, Brickwork COntinues
July 18, 2007
Brickwork Continues, Drywall Arrives

07/19/07 Drywall Progressing
July 19, 2007
Drywall In Process, Plumbing Manifold Complete

07/20/07 Siding and Drywall Continue
July 20,2007
Siding and Drywall Continue

07/21/07 Brickwork and Siding Continue
July 21, 2007
Brickwork and Siding Continue

07/24/07, Siding and Drywall Continued
July 24, 2007
Siding and Drywall Continued

07/27/07 Family Visit
July 27, 2007
Family Visits the House


07/31/07 Well Drilling and Garage Doors
July 31, 2007
Well Drilling and Garage Doors







August, 2007


08/02/07 Power on, Lights and A/C
August 2, 2007
Power on in Basement

08/04/07 Siding Continues
August 4, 2007
Siding Continues

08/07/07 Siding Continues
August 7, 2007
Siding Continues

08/08/07 Drywall Nearly Done
August 8, 2007
Drywall Nearly Done

08/13/07 Well Pump, Drywall Complete, Sat Dishes
August 10, 2007
Drywall Done, Well Pump Installed

08/13/07 Siding Continues, Tile work started
August 13, 2007
Tile Work Started, Siding Continues

08/17/07, Wood Flooring Arrives
August 15, 2007
Siding and Flooring Continue

08/19/07 Tile Prep Work Continues, Tile arrives
August 19, 2007
Tile Arrives, Prep Work Continues

08/20/07 Tile and Wood Floors in Progress
August 20, 2007
Wood and Tile Floors In Process

08/22/07 Wood and Tile Floors In Process
August 22, 2007
Wood and Tile Floors In Process

08/24/07 Tile and Grout flooring Finished
August 24, 2007
Tile and Grout flooring Finished

)8/27/07 Wood Floors Finished, Tile Grouted
August 27, 2007
Wood Floors Sanded and Finished

08/29/07 Siding Continues, Fireplace Brick Started
August 29, 2007
Painting, Fireplace Brick Started, Siding Continues

08/31/07 Painting Continues
August 31, 2007
Brick Fireplace Complete, Painting Continues






September, 2007


09/05/07 Final Concrete Complete
September 5, 2007
Final Concrete Complete

09/07/07 Painting Continues
September 7, 2007
Painting Continues, Hearth Installed

09/09/07 Cabinet Install Begins
September 9, 2007
Cabinets Being Installed

09/13/07 Cabinets and Painting Continued
September 13, 2007
Cabinets and Paint Continued

09/17/07 Cabinets and Painting Continued
September 17, 2007
Cabinets and Paint Continued
09/19/07 WIndow Trim Stained
September 19, 2007
Window Trim Stained

09/21/07 Light Fixtures Installed
September 21. 2007
Light Fixtures Installed

09/24/07 Cabinet and Window Trim
September 24, 2007
Cabinet and Window Trim

09/26/07 Light Fixtures Installed
September 26, 2007
Light Fixtures Installed

09/28/07 Trim and Doors Installed
September 28, 2007
Trim and Doors Installed






Return to our Home Page or Go Back to Our New Home



 Mac and the Mac logo are trademarks of Apple Computer, Inc., registered in the U.S. and other countries. The Made on a Mac Badge is a trademark of Apple Computer, Inc., used with permission.

Made on a Mac

This web site and all content is © 2007 John D Innis

Email me Here!